Construction Report: Sun Tower III (July–October 2025)
construction
progress
31.10.2025
Construction Report: Sun Tower III (July–October 2025)

Construction Report: Sun Tower III (July–October)
Ceramic brick and aerated concrete works
Between July and October, construction progressed from the 15th to the 31st floor:
◾️ Ventilation shaft partitions built with 120 mm ceramic bricks;
◾️ Walls and partitions made of aerated concrete blocks (100–250 mm thick);
◾️ Over 250 m³ of aerated concrete walls completed on floors 23–25;
◾️ Ventilation shaft partitions installed on floors 15–16 and 26–30;
◾️ Masonry of brick walls and partitions completed on the roof level.
Glazing
More than 1,000 m² of double-glazed units of various sizes have been delivered and lifted to the upper floors. Installation preparation is currently underway on floors 23–27.