I. tower construction Progress, February 2019

IN THE MOST CITY CENTER

IN THE COMPLETE SILENCE

27.02.2019
I. tower construction Progress, February 2019

I. tower construction Progress, February 2019

Internal works are well underway in Tower I.

  • Standpipes for storm water intakes have been installed throughout the building.
  • Cement-sand screed works are being carried out on the 21st floor.
  • Walls plastering in common areas on the 23rd floor.
  • Air shaft gas-concrete blockwork on the 23rd floor.
  • Preparatory works are underway on the arrangement of the switchboard room and domestic communications.
  • Works on installation of elevators in elevator shafts have been completed.
  • Works on the installation of an autonomous boiler are coming to an end.