Construction progress 27 Sep 2018

27.09.2018
Construction progress 27 Sep 2018

Construction progress 27 Sep 2018

We are ready to tell you about the latest changes at the construction site.

Tower 1

- The construction of the building is being completed: 22 floors have been built; work is being carried out on the 23rd floor – the area of penthouses.

- Installation of glazing system is being carried out on the 9th floor.

- Work is underway to organize the finishing screed of the floors up to the 6th floor.

- Works started on the facade heat insulation, installation of systems for fixing porcelain stoneware.

- On the operated roof of the stylobate part (the inner courtyard of the complex) the installation of the surface-water drain system is being carried out.

Tower 2

- The foundation works were completed in full, work is underway on the stylobate part.

The organization of external communications on Tower 1 and 2 is coming to the end.

Follow the news from the Bartolomeo Resort Town construction site.

Subscribe to newsletters and stay up to date.

 

Sale of premium apartments

Bartolomeo Resort Town Sales Center

9B, Naberezhna Peremogy St.

Territory of the Bartolomeo, bungalow #1.

Phone: +38 (050) 700 00 57.