Current information from the construction site:

Tower I

 ✔Glazing works are being carried out on the 17th floor.

✔Glazing frame mounting is being carried out on the 18th floor.

✔Works on the hinged ventilated facade are being carried out at the level of the 14th floor.

✔Works on the cement-sand screed are being carried out on the 12th floor.

✔ Installation of the ventilation shaft system is being carried out on the 11th floor.

Tower II

✔ Work is underway on the installation of monolithic reinforced concrete walls of the stiffening core.

 