Tower I. Construction progress, April 2019
construction
progress
16.04.2019
Tower I. Construction progress, April 2019

To date:
- Installation of the Viessmann roof boiler has been completed; testing commissioning works are underway;
- Schindler elevators installation completed;
- Installation of the heat supply substation has been completed;
- Installation of the pumping station is completed;
- Installation of translucent structures is 100% complete;
- Installation of ventilation, smoke removal and air flow systems is completed. The system is fully mounted;
- Hinged ventilated facade mounting works are coming to an end;
- Lightning overvoltage protection works are 100% complete.