I. tower construction Progress, January 2019

10.01.2019
I. tower construction Progress, January 2019

I. tower construction Progress, January 2019

The construction progress. Interior works in the Tower I:

✔ Standpipes for storm water intakes have been installed throughout the building.

✔ Cement-sand screed works are being carried out in apartments on the 18-19 floors.

✔ Cement-sand screed works in common areas are being carried out on the 15-16 floors.

✔ Ventilation duct system installation on the 14th floor.

✔ Works on the sewers construction are being carried out at the level 17-19 floors.

✔ Preparatory works are underway on the arrangement of     the switchboard room and domestic communications.

✔ Work is underway on elevators installation in the elevator shafts.

✔ Work is underway on the autonomous boiler room installation.

 