I. tower construction Progress, January 2019
The construction progress. Interior works in the Tower I:
✔ Standpipes for storm water intakes have been installed throughout the building.
✔ Cement-sand screed works are being carried out in apartments on the 18-19 floors.
✔ Cement-sand screed works in common areas are being carried out on the 15-16 floors.
✔ Ventilation duct system installation on the 14th floor.
✔ Works on the sewers construction are being carried out at the level 17-19 floors.
✔ Preparatory works are underway on the arrangement of the switchboard room and domestic communications.
✔ Work is underway on elevators installation in the elevator shafts.
✔ Work is underway on the autonomous boiler room installation.