Internal works are well underway in Tower I.

  • Standpipes for storm water intakes have been installed throughout the building.
  • Cement-sand screed works are being carried out on the 21st floor.
  • Walls plastering in common areas on the 23rd floor.
  • Air shaft gas-concrete blockwork on the 23rd floor.
  • Preparatory works are underway on the arrangement of the switchboard room and domestic communications.
  • Works on installation of elevators in elevator shafts have been completed.
  • Works on the installation of an autonomous boiler are coming to an end.