Bartolomeo Resort Town Construction Update: September-October 2024

25.10.2024
Bartolomeo Resort Town Construction Update: September-October 2024

Bartolomeo Resort Town Construction Update: September-October 2024

Here's the latest from the construction site:

  • The monolithic frame of the Sun Tower is now 100% complete.
  • Installation of the Belgian-made Reynaers warm aluminum window systems has begun on floors 8-14. These systems are highly eco-friendly and exceptionally durable. Today, you can observe the installation of Guardian safety glass units made from tempered glass, which is four times stronger than regular glass.
  • Masonry of walls and partitions with aerated blocks has been completed, along with the installation of ventilation and smoke extraction shafts on floors 15-18.
  • Work on walls and partitions is ongoing on floors 19-20 and 29-30.
  • Landscaping plans for the amphitheater and waterfront areas are in progress, with relocation of engineering networks completed.
  • Landscaping, retaining wall, and storm drainage projects have been approved.

We’re building with a focus on quality, your safety, and maximum comfort.

Stay tuned for updates to be the first to learn about construction progress and all the important events at Bartolomeo Resort Town. There's much more to come!