Construction progress: may, 2019

12.06.2019
Construction progress: may, 2019

Construction progress: may, 2019

What has been done for the moment:

Tower I

✔Finishing work of common areas in progress;

✔The design project of entrance groups has been approved; preparation works are underway to start finishing works;

✔Works on the improvement of the adjacent territories of the first start-up complex has been started (the porch of the central entrance, the commercial part, the driveway, the sidewalks, the layout of lawns and flower beds, the wiring for the outdoor lighting system, green plantings were ordered).

Tower II

✔The installation of the monolithic reinforced concrete frame of the second start-up complex is well underway (columns, diaphragms, staircases, beams, floor slabs).